Test Plans
A test plan describes the testing for one release: when it starts and ends, who owns it, which test cases are in scope, and how much of that scope has been covered. Where a test run is one executable set of cases, a plan is the release-level view above your runs.
Test Plans hasn't launched yet: the Test Plans tab in your project shows a Coming Soon page for now. This page describes how test plans will work, so you can see where they fit next to test runs. In the meantime, group the cases for a release into a test run.
How plans relate to runs
The plan
Coming soon
What the plan shows
Opening Test Plans
Open your project and click Test Plans in the project menu. The number next to it is the project's plan count.
Until Test Plans launches, this tab shows a Coming Soon page.
The plan list
The header shows the total number of plans. Each plan is a row with:
| Field | What it shows |
|---|---|
| Plan code and name | The plan's identifier and title |
| Dates | Start date → end date |
| Cases | How many test cases are in scope |
| Runs | How many test runs belong to the plan |
| Coverage | The percentage of in-scope cases that have been executed (on the right) |
If the project has no plans, the list says No test plans yet. Click a row to open the plan.
The plan detail view
The header shows the plan code, name, status, start → end dates and owner. Below it:
| Figure | Meaning |
|---|---|
| Coverage | Share of the plan's cases that have been executed |
| Pass rate | Share of executed cases that passed. Shows — (not 0%) when nothing has been executed |
| Cases | Number of test cases in scope |
| Runs | Number of runs in the plan |
— and 0% mean different things. — means nothing has been executed yet; 0% means cases were executed and none passed.
"Scope modified after completion"
If a plan's runs change after the plan was completed, the detail view shows Scope modified after completion. It warns you that a report exported earlier may no longer match what the plan shows now.
Plan statuses
A plan's status describes where it is in its life, not whether tests passed.
- ARCHIVED→DRAFTreopen
| Status | Meaning |
|---|---|
DRAFT | Being prepared: scope and dates are still being set |
ACTIVE | Testing for the release is under way |
COMPLETED | The release's testing is closed |
ARCHIVED | Kept for reference |
Who can manage plans
Everyone on the project can view plans. Managing them is part of a separate test plans permission held by Project Admin, QA Manager and Business Analyst (and workspace Owners and Coordinators), so a Business Analyst can govern a release plan without being able to run tests. See Roles & Permissions.
Troubleshooting
The Test Plans tab shows "Coming Soon"
- Test Plans hasn't launched yet, so every account sees this page for now. Use test runs to group a release's cases in the meantime.
There's no button to create a plan
- The tab is read-only in this release.
Coverage is 0% and pass rate shows "—"
- Test runs can't be attached to a plan yet, so no executions count toward it.
The Test plan field in Create Test Run says "Coming soon"
- Linking a run to a plan isn't available yet.
Next Steps
- Test Runs — Group test cases into an executable set
- Test Cases — The cases a plan covers
- Roles & Permissions — Who can see and manage project work